Westport Calendar & News

S M T W T F S
 
 
1
 
2
 
 
4
 
5
 
6
 
7
 
8
 
9
 
10
 
11
 
12
 
13
 
14
 
 
16
 
17
 
18
 
19
 
20
 
21
 
22
 
23
 
 
25
 
26
 
27
 
 
29
 
30
 
 
 
 

Upcoming Meetings & Events

June 15, 2021 - 6:00pm to 6:30pm
June 17, 2021 - 10:00am to 10:30am
June 17, 2021 - 6:00pm to 6:30pm

Get Involved in the Greater Madison Regional Transportation Plan Update!! »

Join us on Thursday, June 24 from 5:30 to 6:30 for a Public Involvement Meeting. ...

Clean Lakes Alliance Survey »

Let Your Voice Be Heard!Let us know what you think by taking a...

Dane County Land and Water Resources Pier Pickup Schedule »

Pier Pickup ScheduleLakes Mendota, Monona, Waubesa, Kegonsa

Mary Lake Neighborghood Road Improvements 2021 

PROPOSED CONSTRUCTION SCHEDULE

While we do not have a proposed construction schedule as of yet, we anticipate that the project to begin soon and we anticipate full completion in approximately 16 – 18 weeks, weather permitting.  The project plans as well as weekly updates will be posted here

Mary Lake Neighborhood Road Improvements 2021 Final Plans
Mary Lake Neighborhood Newsletter 6/1/21


Town of Westport Water Tower Repainting 

June 10, 2021 - Municipal Well and Pump
Starting work on Well #1, Cobblestone Lane.  Pressure tanks for tower maintenance and controls to be in place until the project is complete.  Up to 90 days.

There will end up being three related, but separate, activities occurring on and around the water tower…all of which are related to the repainting project.

  1. The first task is that the cellular providers (T-Mobile and US Cellular) are relocating their antennas from the tower to a temporary tower so the tank painting contractor can perform its work.  We haven’t visited the site for this, but based on the schedule included in the cellular relocation email (attached), they are scheduled to be working on the temporary tower this week.  Relocation schedule and other information is included in the attached email.  Once the temporary tower is installed, US Cellular is supposed to relocate from the water tower to the temporary tower the week of June 7, 2021 and T-Mobile the week of June 14, 2021.
  2. The second task is that the Town is working directly with a well contractor to provide a pressure tank for the water system.  This will be what maintains pressure in the water system while the water tower is offline.
  3. The third task will be the actual tank repainting project.  I’m enclosing the meeting minutes to this email as well.  Page 5 of 9 of this document includes the Contractor’s proposed schedule for the project.

Once the tank repainting project is complete and the water tower is back in service, the pressure tank (2nd task) and temporary cellular tower (1st task) will need to be removed from the site and then the cellular providers will reinstall their equipment on the water tower.


If you are doing any grading, digging or topography changes near a pond, lake or stream, please contact the Town of Westport or Dane County Land & Water Resources Department to see if there are special permits that might be required. This will help avoid fees and penalties for not following proper procedures.


CTH M, Oncken Road to STH 113, Dane County Virtual Public Involvement Meeting/Presentation - June 2021, Updated Project Information - Scope Change at County K Intersection

County Highway M Improvements


STH 113 (Knutson Drive to STH 19) Improvements